BROWNSVILLE — Cameron County commissioners decided on Tuesday not to move forward with a public hearing to consider a tax abatement for SpaceX’s forthcoming data center in Starbase.
They rejected the bid in a 3-2 vote, with Cameron County Judge Eddie Treviño and Precinct 2 Commissioner Joey Lopez voting in favor of the hearing.
Lopez said during the meeting that the vote was not to approve a tax abatement deal but to move the public hearing forward and get a better look at the numbers, including the cost of the project and how much the tax abatement would be.
“Everyting was just to set up the public meeting so we could have public input too, plus showing the numbers,” Lopez told The Herald. “As of right now with the court, it’s not going to happen, so it’s dead in the water.”
The facility is located within the county’s tax increment reinvestment zone, and the company asked for a 10-year, 100% tax abatement. If approved, SpaceX said in its application that the tax abatement would likely lead the company to expand the project in the future. Without the tax abatement, the company said it would “redirect current and/or future investment to other super compute facility sites outside Cameron County.”
The public hearing on the tax abatement would have taken place during the commission’s regular meeting on Dec. 29.
The first hour of the commission meeting was taken up mostly by county residents and representatives of organizations like the South Texas Environmental Justice Network, Valley Interfaith and Surfrider Foundation urging commissioners to reject the application.
The data center is described in county documents as “natural gas-fired power plant and a co-located super compute facility. The super compute facility will utilize closed-loop cooling systems for efficient water use, and the power plant will provide behind-the-meter power generation to limit the burden of new load on the ERCOT grid.”

The cost of the data center and gas-fired power plant are $24 billion with property tax values of $13.8 billion, according to the application.
SpaceX applied for the tax abatement on Oct. 15 and sent a revised application on Nov. 9. The application puts the start of construction in the fourth quarter of 2026 and completion in the second quarter of 2027. It estimates the number of peak construction jobs at 5,500.