SPI Council maps Convention Center priorities – Port Isabel-South Padre Press


SPI Convention Centre

By JACQI LEYVA-HILL

Special to the PRESS

South Padre Island City Council members met with Broaddus & Associates on Aug. 11 to establish project-management roles, priorities and communication procedures for the proposed Convention Center renovation and annex project, while also discussing expansion options, environmental concerns and financial oversight.

The workshop agenda called for discussion of the project overview, roles and responsibilities, project scope and deliverables, timeline and milestones, budget and financial controls, communication protocols and potential risks.

During public comment, one speaker questioned the project’s costs and requested more detailed accounting of money already spent. He also raised concerns about what he described as a new $3.6 million contract involving Broaddus, at $100,000 per month, which he said had been signed about 10 days earlier, and asked what services the city would receive for that expenditure.

A second speaker, Teresa Yegels of Brownsville, urged the city to preserve the natural area near the Convention Center, saying the location helped spark her interest in birding and warning that losing its birding appeal could discourage birding visitors.

Once the workshop began, council members, city staff and Broaddus representatives identified goals for the project. Councilman Joe Ricco emphasized attracting youth sports tourism during the fall and winter months, citing potential events such as basketball, cheer, dance and other tournaments.

Mayor Patrick McNulty said the city needs additional exhibit space because some associations have outgrown the current facility, but stressed that expansion should be approached in a fiscally responsible manner and designed to remain useful for decades.

Councilwoman Aarin Hartwell also emphasized fiscal responsibility and transparency, saying residents still have questions about project costs and future operating expenses. She asked that communications regarding the project be shared with the full council.

Tourism Director Kelly de Schaun discussed integrating the Convention Center with existing outdoor uses, including birding, windsurfing and public access to sunset views. She also identified reduced maintenance costs, energy efficiency and possible LEED certification as goals. Convention Center staff raised needs including additional storage, updated technology, fire-alarm improvements and expanded generator capacity.

Broaddus representatives presented three conceptual expansion options. Option A included an expanded exhibit hall, storage and other improvements. Option B added ballroom and meeting space, while Option C added additional meeting rooms intended to bring the facility closer to an industry guideline tying meeting-room capacity to exhibit space.

Officials also discussed designing infrastructure so future phases could be added later without requiring major demolition or reconstruction.

Broaddus representatives explained that the project is using the Construction Manager at Risk delivery method. Under that process, subcontractor, material and labor packages would be publicly advertised, with Broaddus describing an effort to obtain multiple bids and evaluate contractors based on overall value rather than price alone.

The city manager’s office was designated as the city’s primary point of contact, with City Manager Randy Smith identified for that role. Broaddus representatives stressed that project changes must follow the established communication process and be authorized in writing before work is performed.